Questions tagged [constraints]

For questions about project or process constraints, or about the Theory of Constraints management paradigm.

Related links:

19 questions
5
votes
4 answers

What is the purpose of the "as late as possible" constraint in MS Project?

I understand that I can use this constraint in MS Project, but really, what is a good use case for this? When does this constraint make sense?
Amrinder Arora
  • 414
  • 3
  • 10
4
votes
4 answers

What can I do when I can't adjust scope, resources, or schedule and a team member wants a raise?

After almost 20y programming and 5y managing I have arrived at a state to be so confused with the basics that I need help from outside! At the project management we have 3 pillars: Scope: features and functionality Resources: costs and…
4
votes
8 answers

When does throwing in people to meet a Project's Scope or Time constraints ever work?

While there's way too much wisdom and anecdotal evidence accumulated over the years that throwing new people into a project to magically close a scope-gap or a schedule-gap is a bad idea, I've noticed that seasoned leaders continue to try this,…
shivsky
  • 205
  • 1
  • 9
4
votes
4 answers

How to deal with a client who does not respect PM practices, yet wants a PM?

Simply put, I have a client who does not respect PM practices. We have a large, high value, multi-stakeholder, multi-variable project. I estimate that if we are not 50% complete by end of February, we need to make some serious decisions (dedicate…
Gryph
  • 304
  • 1
  • 7
4
votes
2 answers

critical chain project management

I want to fully learn about critical chain project management in scheduling construction projects. I've gone through many videos and journals, but can't find any clear cut ideas or proof that shows how exactly critical chain method is different from…
Jagadha
  • 41
  • 1
4
votes
1 answer

How should I schedule around a resource that may be unavailable for up to 5 months a year?

Background: I am managing a Project where I am responsible planning the construction of a visitor center on the peak of a mountain. The Problem: During reading the brief, I have came across the following statement: "Poor weather conditions often…
user3650137
  • 81
  • 2
  • 6
4
votes
4 answers

Should I disclose technical constraints and details to the client?

Background In our Software Requirements Specifications (SRS) we have a clause which states that the user should be able to make push notifications from the website to the mobile devices. Should we inform the client about the constraints of the…
Placeholder
  • 441
  • 1
  • 3
  • 8
3
votes
6 answers

How can you make a project succeed by raising budget?

So I was reading this Answer and it brought to mind a question I've held for a while but never got around to asking. If you've got a late project with fixed scope, schedule, and quality, you're supposed to be able to fix it by increasing budget,…
Sarov
  • 14,643
  • 5
  • 31
  • 60
2
votes
1 answer

Task with specific predecessor and weekday - Project 2003

I'm having trouble to schedule a task that has two date constraints: It must happen 5 days after a precedessor task; It must happen on Mondays. I tried creating and using an specific calendar, that only has Mondays as work days, but it didn't work…
Edmon
  • 23
  • 5
1
vote
3 answers

Iron triangle question..how could extended scope only be mitigated by time?

I have read the following about the Iron trinagle: To add features to a product (scope), you could extend the deadline to make time for the new work (time) or add people to get it done faster (cost). You could also do both! Well, if I extend…
John V
  • 333
  • 1
  • 7
1
vote
5 answers

Iron Triangle / quality triangle - why the middle is said to be non-existant?

I struggle with some interpretations of the model. Some visualizations says that no projects live in the middle of the triangle. But I wonder why? It would mean that the project is of moderate quality, will be deliver in moderate time and with…
Puerred
  • 11
  • 2
1
vote
3 answers

What is "Lead Time"?

I have a task within my project criteria which states: "Purchasing lead-time for the steelwork is estimated at 60-80 days". What does lead time mean? Do I have to make special considerations for this?
1
vote
2 answers

Can you add constraints to a split task in ms projects?

What if I would have a task A, split into three sections. Could I set a finish-finish relationship between task B and the end of the second section of task A? And if not, what would be a recommended path to take?
Jes
  • 57
  • 1
  • 5
0
votes
5 answers

When we decrease budget in iron triangle, is it necessary that scope must decrease?

Say scope remains constant, then if cost decreases, time should increase. But if cost decreases and scope decreases then time should also decrease. Shouldn't it? Is that first figure correct?
puajeh
  • 1
0
votes
1 answer

Why are start constraints being generated when I update the schedule?

When I update MS Project for the current date, the program is generating start constraints on activities that have not started yet. These activities do not need to start at the update Date, but can start later based on the logic and available…
IShunter
  • 1
  • 1
1
2