Questions tagged [ms-project]

Use this generic tag for questions that apply to most versions of Microsoft Project. For version-specific questions, please use an alternate tag instead of the catch-all tag. Version tags currently include: ms-project-2003, ms-project-2007, ms-project-2010, ms-project-2013, and ms-project-2016.

Umbrella and Version-Specific Guidance

Use the generic for questions that apply to most versions of Microsoft Project. For version-specific questions, please use one of the tags below instead of the catch-all tag:

The tag is a catch-all tag for questions about how to use MS Project to manage or track a project. Here are some examples of questions asked by the community that fall under this tag:

NOTE: Do not use for MS Project questions.

See Also

627 questions
15
votes
2 answers

In MS Project, can I create a task whose duration depends on two milestones?

I want to show an ongoing "support" task in MS Project, where the start date is driven by one milestone (test environment available), and the end date is set by another milestone (testing complete). I do not want to enter a duration or an amount of…
Iain9688
  • 6,728
  • 4
  • 21
  • 48
13
votes
7 answers

How can I use MS Project to manage an agile project

We use MS Project to manage a project. Although I know that MS Project is just a scheduling tool, we use it to get the current state of the project. We update the % complete field at the end of every day for tasks and send the total project %…
matrix
  • 323
  • 2
  • 3
  • 10
11
votes
4 answers

Can MS Projects be integrated in SharePoint?

I wonder if it's possible to integrate a template from MS Projects into SharePoint. We have been using this tool to plan and illustrate workpackages. However, since we have moved into a bigger team in remote locations we have been asked by…
yeforriak
  • 333
  • 2
  • 7
11
votes
10 answers

Showing Microsoft Project files to people without Project

The project managers at my company were asked to use Microsoft Project 2013 to track our projects, but many of the business stakeholders do not have Project installed. It looks like I cannot just export the task list or Gantt chart as a PDF. There's…
Daniel
  • 16,656
  • 2
  • 19
  • 49
10
votes
2 answers

Is it possible to link msproject with the TFS system?

I wonder if it is possible to create and manage tasks in microsoft project 2010 and commit the modifications to the TFS project's tasks? It will be practical to raise the percentage of a task in MSProject and send this modification to the TFS…
bAN
  • 235
  • 2
  • 6
8
votes
4 answers

how can I highlight overdue tasks in MS Project 2007

I am using MS Project 2007. I want to highlight overdue tasks in red color. Is there any way to do so?
matrix
  • 323
  • 2
  • 3
  • 10
7
votes
4 answers

Catch-Up Scheduling

Say I have a project X that is due to be complete by Date Y Right now we are 10% behind schedule (Should be say 50% and right now 40%), How can I estimate what level of "effort" is required to catch up? I.E. the original schedule expected 1% of…
onaclov2000
  • 171
  • 1
  • 6
7
votes
5 answers

How can I add contingency to tasks in Microsoft Project?

I'm trying to transfer an existing project plan to Microsoft Project (meaning I can't change how it's organised). Each task has a duration in days then a contingency in days showing how much the task might overrun due to complexity, etc: Task …
parsley72
  • 171
  • 1
  • 1
  • 5
7
votes
2 answers

Why does MS project multiply the duration of tasks?

I've created a recurring task in MS project and I'd like to assign resources (staff) to that resource but when I add the resource(s) to the task the Work hours multiply to extremes and I don't understand why.. For example I have Project Meeting as…
Sheldon
  • 211
  • 1
  • 4
7
votes
3 answers

Should Summary Tasks or Detail Tasks be Predecessors?

When setting up a project, what are the advantages and disadvantages to using Summary Tasks vs Detail tasks as predecessors? If it matters, I am experimenting with MS Project 2010 as a tool.
Kyle Brandt
  • 193
  • 2
  • 6
7
votes
2 answers

In MS Project 2010, is it possible to renumber the task ids?

I'd like the task id field to increment in the same order as the start date, but I have added tasks between existing tasks, so when I sort by start date, the task ids go 1, 8, 15, 2, 4, 5, 7, etc. This is not a big deal but it would just be nice if…
Scott C Wilson
  • 1,143
  • 2
  • 10
  • 20
7
votes
1 answer

MS Project - Span a task over many days AND allow successor to start right after

I am planning my Master thesis through Microsoft Project. Since some tasks can be exhausting (e.g. writing), I would like to distribute some selected tasks over many days. For example, I am estimating that working on a section of the thesis would…
Max H.
  • 71
  • 2
7
votes
2 answers

How to permit multiple Project Managers to update a shared project

I have searched and not found an answer for this (nor did Google help). We are on Project Server 2007. I am running a large program with multiple project managers handling different parts of the program. I would like to allow one of my project…
6
votes
3 answers

Microsoft Project 2010 - Need Project Design Advice

I'm designing an IT project sheet for my department. I have a certain methodology in mind, but i'm trying to translate it into Project's configuration. Here's what I'd like to do: I want to set max untis for each resource in my department to a % of…
I.T. Support
6
votes
3 answers

Using Microsoft Project for managing a Scrum project

I am part of a Scrum team and we are constrained to use Microsoft Project (MSP). I understand that MSP is not primarily an Agile project management tool and I would very much to use something like VersionOne or Rally's tool. However, that is not…
Ather
  • 865
  • 2
  • 6
  • 10
1